Business challenge

Our client needed help to deliver the project on-time and on-budget.

Context

A large pulp and paper producer was building a multi‑billion pulp plant in the middle of their pine and eucalyptus plantation.

Project implementation was complicated by divided responsibilities between 25+ Engineering, Procurement and Construction (EPC) teams, each with multiple subcontractors and a project reporting structure that did not allow for clear visibility and problem resolution.

Business impact

0 weeks
total potential savings (not cumulative) in various critical path reductions

0 days
of delay recovered in principal substation after three weeks of focus to meet critical commissioning date

0%
increased production capacity of concrete supplier

Solution

How we helped

  • Identify key areas for attention and deployment of rapid response team to resolve critical issues
  • Implement an owner's managerial War Room, plus 20+ contractor site War Rooms
  • Train owner's team to conduct daily sessions in War Rooms to control rate, readiness and critical path through relevant construction key performance indicators
  • Identify gaps and problems in contractors' schedules to reduce risks and/or maximise time‑saving ideas

Key Takeaway

  • Gain transparency and alignment for PMO through using strategically‑located visual boards with area‑specific detail cascaded to visually keep track of progress, schedule, ownership, etc.
  • Implement visual schedule to highlight interim deliverables on the critical path, helping EPCs to focus time and resources – on this engagement, we increased the number of concrete trucks dispatched by 8:30am each morning, from less than 6 to 10 trucks
logo
Connect with us
We actively reduce the climate impact from our operations and invest in community-based climate solutions to balance remaining carbon emissions
This system is the property of Accenture and is to be used in accordance with applicable Accenture Policies. Unauthorized access or activity is a violation of Accenture Policies and may be a violation of law. Use of this system constitutes consent to monitoring for unauthorized use, in accordance with Accenture Policies, local laws, and regulations. Unauthorized use may result in penalties including, but not limited to, reprimand, dismissal, financial penalties, and legal action.