Business challenge

Our client needed to remove redundancy, expand capacity and ensure an optimal contracting strategy to provide the lowest capital option.

Context

A major iron ore producer was expanding production at a brownfields operation from 10 to 20 mtpa.

They were concerned about the high capital cost of the expansion project, and also interested in determining the most effective contracting strategy (in a buyer's market) while still appropriately managing risk.

$0m
reduction in capital costs from $800m to $740m

$0m
additional potential capital cost savings available by adopting a minimum technical solution

Solution

How we helped

  • Conduct a value improvement review of the entire project and reduce scope to achieve only core requirements
  • Evaluate the current contracting strategy and market conditions to recommend an optimal contract strategy
  • Identify opportunities to further reduce cost through the exploration of gain sharing and penalty assessment
  • Focus on contract terms to drive project performance management and ensure transparency regardless of contractual approach
logo
Connect with us
We actively reduce the climate impact from our operations and invest in community-based climate solutions to balance remaining carbon emissions
This system is the property of Accenture and is to be used in accordance with applicable Accenture Policies. Unauthorized access or activity is a violation of Accenture Policies and may be a violation of law. Use of this system constitutes consent to monitoring for unauthorized use, in accordance with Accenture Policies, local laws, and regulations. Unauthorized use may result in penalties including, but not limited to, reprimand, dismissal, financial penalties, and legal action.